The Engineer's determination under Sub-Clause 3.7: a checklist

Under FIDIC 2017 the Engineer must act neutrally when agreeing or determining a matter. A determination that skips a step is easy to challenge; one that follows them holds.

Gökhan Güney, Nota Consultants, November 2026

Consult first

Sub-Clause 3.7.1 asks the Engineer to consult the Parties, jointly and separately, and to encourage agreement. Keep a record of each meeting and of what each Party submitted. If there is no agreement within the time limit, the Engineer moves to a determination.

Determine fairly, with reasons

Sub-Clause 3.7.2 requires a fair determination in accordance with the Contract, taking due regard of all relevant circumstances, with reasons and supporting particulars. A figure without reasons invites a Notice of Dissatisfaction.

Keep the clock

Sub-Clause 3.7.3 gives 42 days to reach agreement and a further 42 days to give the determination. If the Engineer gives no notice within the time limit for a Claim, the Claim is deemed rejected, which moves the dispute forward rather than settling it.

Checklist before you sign

  • Was the Notice of Claim given within 28 days (20.2.1)?
  • Was the fully detailed claim received within 84 days, with its contractual basis (20.2.4)?
  • Is the time assessed against the accepted programme, with concurrent delay considered?
  • Is the cost assessed from records, not from claimed rates?
  • Does every item have a reason the Parties can read and check?

After the determination

Clerical or arithmetical errors can be corrected on Notice within 14 days (3.7.4). Either Party may give a Notice of Dissatisfaction within 28 days (3.7.5); otherwise the determination becomes final and binding.

This note is general information, not legal advice for a specific contract.

Need this done on your project?

We prepare or review the document for you, on your letterhead, with a fixed price agreed in writing before we start.

Lit building under construction with a crane at dusk

Need a notice or an RFI written this week?

Send us the facts. We reply with a proposal.

No obligation. Tell us the contract and the problem; we tell you honestly whether we can help.

info@notaconsultants.com
Get a proposalSample documents