FIDIC Red Book and Yellow Book: the time limits a Contractor must track

Most time limits are the same in both books. What changes is who carries the design, and the notices that come with it.

Gökhan Güney, Nota Consultants, November 2026

1. The same in both books

  • Notice of Claim: 28 days after becoming aware of the event (Sub-Clause 20.2.1).
  • Fully detailed claim: 84 days after becoming aware (Sub-Clause 20.2.4).
  • Initial programme: 28 days after the Commencement Date (Sub-Clause 8.3).
  • Monthly progress report: within 7 days after the end of each month (Sub-Clause 4.20).
  • Consultant's determination: 42 days, and a Notice of Dissatisfaction within 28 days after it (Sub-Clauses 3.7.3 and 3.7.5).

2. What the Red Book adds

Under the Red Book the Employer designs. The Contractor's main risk is late or changing design information, so the notice for delayed drawings or instructions (Sub-Clause 1.9) matters most. Every drawing that arrives late, and every revision that changes work already planned, needs its own notice and its own record.

3. What the Yellow Book adds

Under the Yellow Book the Contractor designs to the Employer's Requirements. Errors in those Requirements have their own notice (Sub-Clause 1.9), and the Contractor's design documents go to the Consultant for review, usually with a review period of 21 days (Sub-Clause 5.2.2). A design submission that misses its slot in the programme can delay procurement and site work behind it.

4. Read the Particular Conditions first

Most of these periods can be changed in the Particular Conditions, and many projects do change them. Before the first notice is needed, put every period from your own contract into one calendar, with who sends what to whom. That calendar is worth more than any general rule, including this one.

This note is general information, not legal advice for a specific contract.

Need this done on your project?

We prepare or review the document for you, on your letterhead.

Lit building under construction with a crane at dusk

Need a notice or an RFI written this week?

Send us the facts. We reply with a proposal.

No obligation. Tell us the contract and the problem; we tell you honestly whether we can help.

info@notaconsultants.com
Get a proposalSample documents